Automated labelling and in-process reporting at an aerated concrete plant

CE labels and detailed in-process production reports generated automatically from production data and the Business Central product master data, built on the REACH Data Platform.

Customer
Building materials manufacturer – greenfield aerated concrete plant
Industry
Building materials manufacturing
1–2 sto produce one label (previously 5–10 s)
~2000labels a day at peak times, without manual work
1–2 peoplelabour replaced (order-of-magnitude estimate)

In brief

Challenge

The turnkey production line could neither print labels nor produce in-process production reports: CE labels were set by hand on the HMI, and reports were compiled manually with limited detail.

Solution

The REACH Data Platform collects data from the mixer, the cutting machines and the autoclaves, and forms the basis for the Business Central integration, product identification, automatic labelling and reporting.

Result

A label takes 1–2 seconds instead of 5–10, several hours of manual work a day at peak times were eliminated, and the reports are produced automatically every hour, shift, day and month.

Starting point – manual labelling and reporting

A building materials manufacturer built a new, greenfield aerated concrete plant next to its existing production plant. The plant, which produces aerated concrete (AAC – autoclaved aerated concrete) blocks, wall panels and lintels, was bought as a turnkey system from a supplier that has already installed similar plants in many parts of the world. The production line covers the entire aerated concrete production process, from concrete mixing and casting, through resting, cutting and autoclaving, to the packaging of the finished products.

The turnkey solution, however, did not include two capabilities that are indispensable for the customer's day-to-day operation. It could not print labels on the finished products automatically, and it did not produce in-process production reports either. Both had to be done by hand.

The labels of the finished products have to carry the data content prescribed by the relevant standard, which is why they are also called CE labels. Operators had to set this label data manually on the HMI of the production line's PLCs, then print the labels and place them on the packaging. The process was slow and carried several opportunities for error: a typo or wrong product data could end up on the label during manual setup. Labels applied by hand also needed special attention when goods were received into stock. In the warehouse process, products were booked into stock with manual barcode scanning, and the same label was sometimes scanned several times.

Producing in-process production reports was also manual. Reports compiled by hand could not offer the depth and level of detail that production and quality assurance engineers needed to understand and optimise the process. Raw material consumption, the duration of work steps and the characteristics of the products made were therefore not available with the required level of detail and regularity.

The project was initiated by the plant's production engineers and quality assurance engineers. The aim was to replace a significant part of the manual work of labelling and reporting, and thus save human resources. The plant initially operated with manual labelling and reporting, and automation was introduced gradually during its trial and live operation. The customer asked Mortoff to build the solution. We worked in close cooperation with the supplier of the production line on the data handovers and the design of the PLC interfaces.

Implemented solution – automatic labels and reports

Mortoff implemented a solution that automatically generates CE labels from the plant's production data and from the product master data of the enterprise management system, prints them and applies them to the packaging, and also produces detailed in-process production reports from the same data. The backbone of the solution is the Mortoff REACH Data Platform, which collects and stores the production data. Built on top of it are customer-specific components that handle the Business Central integration, product identification, label generation and reporting.

Data collection and integration with the production line

The system collects data from three key process units of the plant and from the product master data: the concrete mixing station, the cutting machines and the autoclaves, as well as the product master data managed in Microsoft Business Central. The PLCs installed in the plant are connected via an OPC UA interface. The concrete mixing and casting system is linked through database synchronisation, which feeds the basic data of completed castings and raw material consumption into the system. The Business Central product master data is also synchronised into the solution, so it always works with the current product master.

Product identification and automatic label generation

Label generation is based on accurate product identification. Every basic product type (block, panel, lintel) has 5–7 parameters, with which the corresponding item of the product master can be unambiguously identified from the production data. The system generates the content of the label from the product master data of the identified product. Each of the main product families (block, panel, lintel) has its own label template.

The label is created at the end of the packaging process, after foil wrapping. A printer prints it, and applying the label to the packaging is also automatic, so operators do not have to deal with setting the label data, with printing or with applying it.

In-process reporting

The reporting component produces reports covering the entire production process: concrete mixing, resting, cutting, autoclaving and the other process steps. The raw material consumption data of the reports includes not only the direct raw materials of the product (for example sand) but also other materials consumed during production, such as cutting wire, packaging material and pallets. The system also measures the duration of the individual work steps, with minimum, maximum and average values, and produces statistics on the products made, for example on dimensions and density.

Reports are produced hourly, per shift, daily and monthly in Excel format and are placed on a network drive. Users can modify the look and structure of the Excel templates to suit their own needs, and the reporting application follows the changes immediately. The daily report is also sent by e-mail to the head of the process engineers.

Exception handling and transparency

If a product cannot be identified, for example because incomplete data arrives due to a data connection error, the system signals an error to the printer, and the label can then be printed manually. A status page gives an overview of the state of the system's data connections, so users can check at a glance whether the data connections are working properly.

Architecture and operation

The solution runs on the plant's own on-premises infrastructure. The components of the REACH Data Platform collect and store the production data, while separate components built for the customer's processes and integrations handle the Business Central integration, product identification, label generation and reporting. All functions of the solution are currently in live operation.

Results – less manual work, detailed data

The most direct, quantifiable effect of the project is the speed-up of labelling and the elimination of the related manual work. Producing a label by hand took 5–10 seconds; the automatic system does it in 1–2 seconds. At peak times, the plant produces about 2,000 labels a day – one for every pallet packed. Manual labelling therefore meant several hours of work a day at peak times. Automation has practically eliminated this, which corresponds to the labour requirement of roughly 1–2 people. The packaging of the finished products also became faster.

MetricValue
Time to produce one label by hand5–10 seconds
Time to produce one label automatically1–2 seconds
Peak daily label countapprox. 2,000 labels (pallets)
Labour replaced (order-of-magnitude estimate)1–2 people
Introducing a new product type in labelling and reportingapprox. 2 working days

The project's most important metrics

The solution also improved traceability and data quality. When labelling was manual, the same label was sometimes booked into stock several times with manual barcode scanning. With automatic labelling, this error does not occur. The content of the label now comes from the product master data and the production data, so the risk of typos made during manual setup is eliminated.

The main added value of the in-process production reports is their level of detail. Manual reports could not be produced in as much depth as the current, automatically generated ones, so the two states cannot be compared directly. Production and quality assurance engineers today see raw material consumption across the entire process, including auxiliary materials, the minimum, maximum and average values of the durations of work steps, and statistics on the dimensions and density of the products made. The reports are available broken down by hour, shift, day and month, and users can shape the report templates to their own needs.

The solution is also an advantage when introducing new products. Because the label comes from the Business Central product master data, introducing a new product within a product type (block, panel, lintel) means no additional work on the solution's side: it is enough to create it in the product master, from where it is synchronised into the system and can be used immediately on labels and in reports. Introducing a completely new product type takes approximately two working days at the level of labelling and reporting.

Operation of the system is helped by the status page, which shows the state of the data connections at a glance. In case of missing data, the possibility of manual label printing ensures that packaging does not stop.

Overall, the project gave the aerated concrete plant an automated labelling and reporting capability that was not originally included in the turnkey production line. Labels set and applied by hand were replaced by labels generated automatically from the production data and the Business Central product master data and applied automatically, and manual reporting was replaced by detailed, automatic in-process reports. The customer can thus run the plant with less manual work, more reliable traceability and far greater visibility into the production process.